What is the importance of a test run before using a concrete laser leveling?

Compared with the laser leveling / leveling machine, the trial run process is an experimental process before it is officially put into use, and only the equipment that has been successfully tested can be officially put into use. It can be seen that in the process of using the laser leveler, the test run is a very important step. In order to help everyone realize the necessity of this step, the following article mainly introduces the importance of the test run process before using the laser leveling.
1. Clean the laser leveling machine, the surface of each component, and check whether all joints are firmly fastened.
2. All lubricating parts of the laser leveling machine are filled with oil, check whether the electrical system is intact, whether the limit switch is set correctly, whether the connection is reliable, no-load test, and the lifting motor is lifted and lowered no less than 10 times, requiring flexible transmission and high precision , stop, the resistance of the main drive is stable, and the sound is normal. After the empty car is put into trial operation, a load test is carried out.
3. Adjust the position of the frame according to the width of the corrected I-beam flange plate, and adjust the correct position of the guide rod according to the thickness of the plate.
4. Start by the power supply, start the laser leveling / leveling machine to run dry, ensure the normal operation of the parts and components of each transmission part, no cassette tape, no overheating, load can be loaded, and the welded H-beam is suspended on the roller table by a row crane superior.
5. Start the drive roller to transport the steel into the laser leveler/ leveling machine. This end exceeds the frame leveler, and this end stops after exceeding the center of the correction wheel by about 150mm. Press the upper roller to reduce the linkage. When the upper roller touches the workpiece Immediately stop, and then press the upper and lower pressure rollers, the pressure may have errors, and can be adjusted at any time.
6. Correctly adjust the amount of depression during the test run of the laser leveling / leveling machine. The dial of the screw rod is indicated as 0.5mm per grid, and the amount of over-deformation under pressure must not exceed 1mm. However, the adjustment of the upper pressure roller can only be done during the stop process. Carried out, the output of the workpiece is about 200mm, and the flange plate after the initial correction is perpendicular to the web to prevent over-correction.
7. If it is necessary to adjust the correction amount, retract the workpiece into the main unit (the end is about 150mm from the center of the correction wheel) to adjust the shrinkage of the correction roller, start the main drive motor, and perform normal correction output. If multiple corrections are required on one side, the workpiece should be stopped immediately after the end of the workpiece is about 100mm from the center of the correction wheel, and the workpiece should return to the front end of the front end about 150mm beyond the center of the correction wheel.
The above article is all the content introduced by the manufacturer about the importance of the test run process before using the laser leveling machine. Do you understand it? If you feel interested in our products after reading the article, you can call us for details, thank you for your reading and support.
Share this article

About the Author: Shandong Vanse Machinery Technology Co., Ltd.
Shandong Vanse Machinery Technology Co., Ltd. is a high-tech manufacturer specializing in concrete construction machinery, including laser screeds and related equipment. The company integrates R&D, production, and global sales, with products exported to over 60 countries and widely used in infrastructure projects worldwide.
Previous Post
Next Post
Related Articles