Discussion on the floor construction technology using laser leveling machine

February 24, 2025

VANSE YZ28-4S concrete laser leveling machine
Discussion on the floor construction technology using laser leveling machine 2
The following is a discussion on the process of using laser leveling machine for floor construction:
 

1. Construction preparation:
– Equipment debugging: Perform a comprehensive inspection and debugging of the laser leveling machine to ensure its good performance and normal operation.
– Benchmark setting: Make at least 2 fixed benchmark leveling points based on the original leveling point to control the floor elevation.
– Site cleaning: Remove debris, garbage, etc. in the construction area to ensure that the base is flat and clean.
– Material preparation: Prepare the required concrete, hardened materials, etc., and ensure that their quality meets the requirements.
2. Concrete paving:
– Within the effective range of the telescopic arm of the laser leveling machine, first spread the concrete roughly by hand, and the thickness is slightly higher than the design elevation.
– Then the laser leveling machine completes the vibration, compaction, and leveling work at one time to ensure that the concrete surface is flat and uniform.
3. Spreading of hardened materials:
– When the concrete is initially set (a 3-5mm mark is left by the finger pressure test), first spread 2/3 of the hardened aggregate (non-metallic aggregate or metal aggregate and alloy aggregate) evenly in the vertical and horizontal directions to allow the material to fully absorb the moisture in the concrete.
– Use a smoothing machine to smooth it, and then spread the remaining 1/3 of the hardened aggregate evenly, smooth it several times and then smooth it. The corners should be smoothed and smoothed with a manual trowel.
4. Maintenance and cutting of expansion joints:
– After the construction is completed, the curing agent (water plus film, wax, sealing curing agent) can be used for curing, and the curing time should not be less than 7 days.
– Cutting should be carried out at the earliest time while ensuring that the cutting does not burst the edge. Generally, the cutting should be completed 1-3 days after completion depending on the weather conditions and the concrete conditions at the time to prevent irregular cracking. The spacing of the cutting joints is determined according to the distance between the workshop columns, and it is preferably no more than 6m. The cutting line should be uniformly marked to ensure that the cutting joints are neat and straight, and the cutting depth should be at least 1/3 of the thickness of the concrete base.
5. Flatness test:
– Use f-meter or measuring equipment of the same level to test the flatness to ensure that the flatness of the floor meets the requirements.
– Repair the uneven areas detected in time.
6. Seam filling:
– Before using the floor, fill the cut seams with seam filling glue to prevent debris from entering the seams and affecting the service life of the floor.

The use of laser leveling machine for floor construction can greatly improve the construction efficiency and quality, reduce manual errors, and make the floor flatter and smoother. During the construction process, the operation should be carried out strictly in accordance with the construction process requirements to ensure construction safety and quality.

 

Share this article

About the Author: Shandong Vanse Machinery Technology Co., Ltd.

Shandong Vanse Machinery Technology Co., Ltd. is a high-tech manufacturer specializing in concrete construction machinery, including laser screeds and related equipment. The company integrates R&D, production, and global sales, with products exported to over 60 countries and widely used in infrastructure projects worldwide.

Shandong Vanse Machinery

Leading manufacturer specializing in high-performance concrete laser screeds, telescopic arm flatwork handlers, and mechanical ride-on power trowels.

Post overview

Need Machine Guidance?

Speak directly with Shandong Vanse field specialists for tailored equipment quotes and site planning.

Contact Us Today

Related Articles

You Might Also Like